Which statement best describes the Sprint Backlog as the output ot the Sprint Planning? (choose the best answer)
Correct Answer: D
According to the Scrum Guide, the Sprint Backlog is the Developers' plan for the Sprint, as it contains all the Product Backlog items selected for the Sprint and a plan for delivering them. The other options are not valid descriptions of the Sprint Backlog, as they are either incorrect (such as having a designated owner, being ordered by the Product Owner, or being a complete list of all work) or unnecessary (such as estimating each task in hours).