Valid Field-Service-Consultant Dumps shared by ExamDiscuss.com for Helping Passing Field-Service-Consultant Exam! ExamDiscuss.com now offer the newest Field-Service-Consultant exam dumps, the ExamDiscuss.com Field-Service-Consultant exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com Field-Service-Consultant dumps with Test Engine here:
An extreme weather situation impacted both the volume of open work and the number of available resources at Universal Containers. Which approach should a Consultant recommend to realign available resources with open work?
Correct Answer: C
Explanation Global optimization is a feature that allows rescheduling multiple service appointments at once based on predefined criteria such as emergency priority, travel time, or skills[194]. Global optimization would allow Universal Containers to realign available resources with open work by running an optimization job that prioritizes emergency work and assigns it to the best available resources[195]. Resource Schedule Optimization is a feature that allows scheduling service appointments for individual resources based on their availability and preferences[196]. Resource Schedule Optimization would not allow Universal Containers to realign available resources with open work because it does not consider multiple resources or service appointments at once. Emergency scheduling is a feature that allows creating and assigning emergency service appointments to the best available resources[197]. Emergency scheduling would not allow Universal Containers to realign available resources with open work because it does not reschedule existing service appointments. Customer First scheduling is a feature that allows prioritizing customer preferences and satisfaction when scheduling service appointments[198]. Customer First scheduling would not allow Universal Containers to realign available resources with open work because it does not prioritize emergency work or reschedule existing service appointments. References: https://help.salesforce.com/s/articleView?id=sf.fs_optimization_overview.htm&type=5 https://help.salesforce.com/s/articleView?id=sf.fs_optimization_global_overview.htm&type=5 https://help.salesforce.com/s/articleView?id=sf.fs_resource_schedule_optimization_overview.htm&type=5 https://help.salesforce.com/s/articleView?id=sf.fs_scheduling_emergency_overview.htm&type=5 https://help.salesforce.com/s/articleView?id=sf.fs_scheduling_customer_first_overview.htm&type=5
Recent Comments (The most recent comments are at the top.)
Recent Comments (The most recent comments are at the top.)
C is correct