Your approved cost baseline has changed because of a major scope change on your project. Your next step should be to______________
Correct Answer: B
Explanation/Reference: Explanation: Before a revised cost baseline leading to a budget update can be prepared, it is necessary to issue a change request, which may include preventive or corrective action. These change requests then are reviewed and processed through the Perform Integrated Change Control process.