For complex procurement items, often contract negotiation can be an independent process. An example of an input if such a process is used is______________
Correct Answer: A
Explanation/Reference: Explanation: Issues or an open item list are examples of inputs if contract negotiation is an independent process. Outputs are documented decisions. While contract negotiations may need to be a separate process for complex procurements, for simple procurement items, the terms and conditions of the contract can be fixed and nonnegotiable.