Change requests include a group of potential changes to a project. Types of change requests include all the following EXCEPT______________
Correct Answer: B
Explanation/Reference: Explanation: Defect repairs, corrective actions, and preventive actions are types of change requests that occur on a project. Maintenance requests typically would be outside the scope of the project itself.