Valid PMP Dumps shared by EduDump.com for Helping Passing PMP Exam! EduDump.com now offer the newest PMP exam dumps, the EduDump.com PMP exam questions have been updated and answers have been corrected get the newest EduDump.com PMP dumps with Test Engine here:
On your project, scope changes, constraints, assumptions, integration and interface requirements, and overlapping roles and responsibilities pose communications challenges. The presence of communication barriers is most likely to lead to______________
Correct Answer: D
Explanation/Reference: Explanation: Barriers to communication lead to a poor flow of information. Accordingly, messages are misinterpreted by recipients, thereby creating different perceptions, understanding, and frames of reference. Left unchecked, poor communication increases conflict among project stakeholders, which causes the other problems listed to arise. Then, the project manager must work actively to resolve conflicts so disruptive impacts are prevented.