Information received from stakeholders concerning project operations can be distributed and used to modify or improve future performance of the project. This modification or improvement is done as an update to organizational process assets during which following process?
Correct Answer: C
Explanation/Reference: Explanation: Feedback from stakeholders is an example of an organizational process asset to update as a result of the manage communications process.