Closing a project phase should not be delayed until project completion because______________.
Correct Answer: A
Explanation/Reference: Explanation: Closure includes collecting project records, ensuring that the records accurately reflect final specifications, analyzing project or phase success and effectiveness, and archiving such information for future use. Each phase of the project should be properly closed while important project information is still available.