You are responsible for a project in your organization that has multiple internal customers. Because many people in your organization are interested in this project, you realize the importance of______________
Correct Answer: B
Explanation/Reference: Explanation: On most projects, communications planning should be performed very early such as when the project management plan is prepared. This approach then allows appropriate resources, such as time and budget, to be allocated to communications activities.