A program steering committee has initiated an 8-year overseas infrastructure construction program. This program will compliment several other overseas programs already underway. The three key engineers have already been assigned to other programs and are unavailable to commit to the new program. What should the program manager do?
Correct Answer: B
Reporting the resource gap to the program sponsor and collaborating on a solution ensures appropriate attention and support from leadership to address the critical staffing challenge, aligning with organizational priorities and resource availability.