A program manager is leading an overseas bullet train program across multiple countries. The program has been successful for a long time owing to the program team's technical expertise and rigorous planning. However, one country's terrain is complex and its mountains are steep which will increase the risk for the whole program. What should the program manager advise the program sponsor to do?
Correct Answer: C
Advising the program sponsor to respond to foreseen risks and activate contingency reserves proactively addresses the increased risk due to the challenging terrain, ensuring resources are available to manage potential issues and protect overall program success.