Based on this matrix, which of the following ideas should the team address first?
Correct Answer: C
Based on the matrix provided, ideas 2 and 5 should be addressed first because they are in the quadrant that represents both high impact and high feasibility. Prioritizing ideas that are both highly feasible and likely to have a significant impact ensures that the organization can quickly and effectively implement changes that will yield the most benefit.
* High Impact and High Feasibility: Ideas in this quadrant are typically the most promising because they are not only achievable (high feasibility) but also expected to produce meaningful improvements (high impact).
* Strategic Prioritization: Addressing these ideas first allows the team to generate quick wins, which can build momentum and support for further quality improvement efforts.
* Comparison to Other Options:
* A. 1 and 7: High impact but low feasibility-these ideas might be more challenging to implement and could require more resources or time.
* B. 3 and 4: Low impact and low feasibility-these ideas are neither easy to implement nor likely to have a significant effect, making them lower priorities.
* D. 6 and 8: High feasibility but low impact-while these ideas are easier to implement, their impact might be minimal, so they should not be the primary focus initially.
References: NAHQ materials on prioritization in quality improvement emphasize the importance of focusing on initiatives that combine high impact with high feasibility to optimize resource use and maximize outcomes.
=========