Which of the following is the MOST important reason to revisit a previously accepted risk?
Correct Answer: C
The most important reason to revisit a previously accepted risk is to ensure that the risk levels have not changed. A previously accepted risk is a risk that the organization has decided to tolerate or retain without taking any further action, because the risk is either low or unavoidable, or the cost or effort of mitigation outweighs the potential benefit. However, risk acceptance is not a static or permanent decision, as the risk levels may change over time due to various factors, such as new threats, vulnerabilities, impacts, or opportunities. Therefore, it is essential to revisit a previously accepted risk periodically or when there is a significant change in the internal or external environment, to verify that the risk is still within the acceptable range and that the risk acceptance rationale is still valid. If the risk levels have increased or decreased, the organization may need to revise the risk acceptance decision and consider other risk response options, such as avoidance, reduction, sharing, or exploitation. The other options are not the most important reason to revisit a previously accepted risk, although they may be relevant or necessary depending on the context and nature of the risk. Updating risk ownership is a part of the risk governance process, which ensures that the roles and responsibilities for managing the risk are clearly defined and assigned, but it does not affect the risk levels or the risk acceptance decision. Reviewing the risk acceptance with new stakeholders is a part of the risk communication process, which ensures that the risk information and the risk acceptance rationale are shared and understood by the relevant parties, but it does not change the risk levels or the risk acceptance decision.
Ensuring that the controls are still operating effectively is a part of the risk monitoring and review process, which ensures that the risk response actions are implemented and maintained properly, but it does not apply to the accepted risks, as they do not have any additional controls. References = Understanding Accepted Risk - SC Dashboard | Tenable, Risk Acceptance - ENISA, Accepting Risk - Overview, Advantages, Disadvantages, Alternatives