Business management is seeking assurance from the CIO that IT has a plan in place for early identification of potential issues that could impact the delivery of a new application Which of the following is the BEST way to increase the chances of a successful delivery'?
Correct Answer: D
The best way to increase the chances of a successful delivery of a new application and to assure the business management that IT has a plan in place for early identification of potential issues is to include business management on a weekly risk and issues report. A risk and issues report is a document that summarizes the current status, progress, and challenges of the IT project, as well as the actions and resources needed to address them. A risk and issues report helps to communicate and align the expectations and objectives of the IT and business stakeholders, and to facilitate timely and effective decision-making and problem-solving. A risk and issues report also helps to monitor and control the project scope, schedule, budget, and quality, and to ensure that the project delivers the desired value and benefits to the organization. The other options are not as effective as including business management on a weekly risk and issues report, although they may be part of the IT project management process or outcomes. Implementing a release and deployment plan, conducting comprehensive regression testing, and developing enterprise-wide key risk indicators (KRIs) are all activities that can help to ensure the quality and reliability of the new application, but they do not necessarily involve the business management or provide assurance for the early identification of potential issues. References = Risk and Information Systems Control Study Manual, Chapter 5, Section 5.4.1, page 5-32.