Valid PMI-RMP Dumps shared by ExamDiscuss.com for Helping Passing PMI-RMP Exam! ExamDiscuss.com now offer the newest PMI-RMP exam dumps, the ExamDiscuss.com PMI-RMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMI-RMP dumps with Test Engine here:
While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?
Correct Answer: C
Biases during risk identification can skew the perception of potential risks and their triggers. To mitigate this, the risk manager should rely on objective data, such as published operational experience reports, which provide historical data and insights into what has triggered risks in similar projects. This approach reduces the influence of biases and ensures that risk identification is based on empirical evidence rather than subjective judgments. Using these reports aligns with best practices in risk management, where decisions are data-driven and supported by documented experiences, reducing the likelihood of overlooking critical risk triggers.