Valid PMI-RMP Dumps shared by ExamDiscuss.com for Helping Passing PMI-RMP Exam! ExamDiscuss.com now offer the newest PMI-RMP exam dumps, the ExamDiscuss.com PMI-RMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMI-RMP dumps with Test Engine here:
When approving the risk contingency budget for a project, the CEO notices each team has a different approach to report risks and their impacts. The CEO decides to create a new centralized risk management function to help resolve the problem. How does centralizing the risk management function help resolve the problem?
Correct Answer: B
Centralizing the risk management function enables the organization to have a consistent approach to reporting risks and their impacts. This allows for better monitoring of the impact against the overall project risk exposure, which helps in making informed decisions and allocating resources effectively. According to the PMI-RMP Exam Content Outline1, one of the tasks in the domain of risk governance is to "establish and maintain a centralized risk management function to support the project and organizational objectives". A centralized risk management function can help resolve the problem of inconsistent risk reporting by providing a common framework, methodology, and standards for risk management across the organization. One of the benefits of centralizing the risk management function is that it allows monitoring the impact of individual project risks against the overall project risk exposure, as well as the organizational risk appetite and tolerance. This can help the CEO and other senior management to make informed decisions and allocate resources accordingly. Therefore, the best answer is B. References: 1: PMI-RMP Exam Content Outline, page 6.