Question 22/94

The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (94q)
Question 1: A project manager of an IT company is assigned to a project ...
Question 2: A risk management professional is in the process of categori...
Question 3: During the design phase the project team is exploring variou...
Question 4: While implementing the risk response plan for a previously i...
Question 5: A project team does not understand why a very low probabilit...
Question 6: A risk manager has identified multiple risks in an innovatio...
Question 7: A project manager has requested the risk manager's support i...
Question 8: A project manager wants to work on understanding the project...
Question 9: In a highly dynamic project environment, the project manager...
Question 10: A risk manager is preparing for the first meeting with their...
Question 11: An organization is embarking on a multi-million-dollar proje...
Question 12: A risk manager is confident that they have identified and qu...
Question 13: A new risk manager has been assigned to a delayed strategic ...
Question 14: When selecting strategies as an activity of Plan Risk Respon...
Question 15: An undocumented risk is realized during the rollout of a new...
Question 16: A project manager identified a risk of communication issues ...
Question 17: A project manager wants to introduce a new technology to imp...
Question 18: During project planning, a risk is identified for which the ...
Question 19: A project manager is educating the project team on risk mana...
Question 20: An organization with a large computer network identified a p...
Question 21: A complex project that had hundreds of risks is almost done....
Question 22: The project risk manager on a large firm fixed priced (FFP) ...
Question 23: A risk manager has a well-structured risk management process...
Question 24: During the risk management planning, key stakeholders recomm...
Question 25: During a project progress meeting, a project team member is ...
Question 26: Project stakeholders can often be risk averse with little to...
Question 27: A risk manager for a new product development project has wor...
Question 28: An organization performs an annual strategies and initiative...
Question 29: One project in a program needs to be completed in 6 months b...
Question 30: The project manager wants to use an objective method to eval...
Question 31: A project has consistently been lagging in cost performance ...
Question 32: A project manager has been assigned to a project that is jus...
Question 33: Business rhythm can fluctuate greatly between different indu...
Question 34: A project manager is developing the risk register and works ...
Question 35: The project manager and the risk manager of a new project to...
Question 36: A risk manager on an infrastructure project gathers and anal...
Question 37: Upon reviewing the risk analysis results, the project manage...
Question 38: it typically takes 5 hours to perform a complete home inspec...
Question 39: A core project team is working on unrelated tasks in advance...
Question 40: After completing the risk register, many team members feel t...
Question 41: An external vendor needs to be contracted to provide additio...
Question 42: The project's customer has stated the project must be comple...
Question 43: After presenting a list of risks to the major project stakeh...
Question 44: Some project risks are applicable for the project's lifecycl...
Question 45: A project manager managing a high-risk rating project was ju...
Question 46: While executing an oil extraction project in an environmenta...
Question 47: Members of a project team are not taking their risk manageme...
Question 48: In a large industrial business, an on-going system developme...
Question 49: A risk manager and relevant stakeholders have completed a ri...
Question 50: What is an example of legal and regulatory requirements and/...
Question 51: A stakeholder is asking a project team to hire an external v...
Question 52: The project manager has completed four projects all with sim...
Question 53: A project manager is working on a construction project. Base...
Question 54: A mega facility development project is evaluating some optio...
Question 55: During a meeting to develop the risk management plan, the ri...
Question 56: A company has implemented a policy requirement for employees...
Question 57: A company has a project whose objective is to extract gold r...
Question 58: A new risk manager has been hired on a project and meets wit...
Question 59: A project manager has just been assigned to a new project. T...
Question 60: At an oil and gas company, a major unified management inform...
Question 61: Three months into a program, multiple workstreams are showin...
Question 62: While performing risk identification exercises, the risk man...
Question 63: An organization that spans across different countries underg...
Question 64: A risk manager has to inform a project sponsor of the expect...
Question 65: A risk manager is managing risks in a project. During the in...
Question 66: A newly assigned risk manager realizes that a project has un...
Question 67: After starting a new pipeline project, a risk manager schedu...
Question 68: A risk management professional is currently facilitating the...
Question 69: A highly complex project is about to start Considering that ...
Question 70: During the project's lifecycle, project risk managers must m...
Question 71: A company manages confidential customer information, and a d...
Question 72: A new risk manager has been hired on a project and meets wit...
Question 73: While developing a risk management plan for a complex progra...
Question 74: Several key stakeholders approach the project manager with c...
Question 75: A risk manager has noticed that response actions are not wor...
Question 76: A risk manager has been assigned to a project constructing a...
Question 77: An agriculture government agency faces different challenges ...
Question 78: The risk manager for an IT project developing a software app...
Question 79: The project manager leading a company's digital signature in...
Question 80: A project manager realizes the team undertaking the project ...
Question 81: There is confusion among risk action owners on a project abo...
Question 82: During project execution, a project manager invites the stak...
Question 83: A risk manager is reviewing documentation for a project foll...
Question 84: Product testing can be done in multiple ways. A few project ...
Question 85: In a large enablement project with strict time lines, risks ...
Question 86: A project is In the initiation phase. The project stakeholde...
Question 87: The risk manager conducted an updated Monte Carlo simul-atio...
Question 88: A risk manager for a large project has completed documenting...
Question 89: During the monthly executive review meeting, the project spo...
Question 90: A project manager for a large product development project as...
Question 91: A risk manager is managing risks of a mission critical appli...
Question 92: A project manager for a predictive project just received a s...
Question 93: When approving the risk contingency budget for a project, th...
Question 94: A certain risk is identified for a major project, and the ri...