A risk manager for a new product development project has worked diligently with stakeholders and the project team to identify and document risks. These project risks vary widely in probability and impact. Which three actions should the risk manager take to inform the identification of resource requirements for individual risk responses? (Choose 3).
Correct Answer: A,B,E
To effectively inform the identification of resource requirements for individual risk responses, the risk manager should undertake the following actions: 1. Conduct Decision Tree Analysis: Collaborate with the project team to perform decision tree analysis for each risk or related set of risks. This technique involves mapping out different decision paths and their possible outcomes, including associated risks, probabilities, and impacts. By visualizing these scenarios, the team can evaluate the potential consequences of various decisions and choose the most effective risk response strategies. 2. Calculate Expected Monetary Value (EMV): Determine the EMV for each identified risk by multiplying the probability of occurrence by the potential financial impact. This quantitative analysis provides a monetary value representing the average expected loss or gain from a risk. Utilizing EMV calculations aids in justifying and allocating appropriate project reserves to address potential risks, ensuring that sufficient resources are available for effective risk management. 3. Prioritize High-Impact Risks: Allocate attention and resources primarily to risks that pose the highest potential impact on the project. By focusing on high-impact risks, the team ensures that critical threats are addressed promptly and effectively, optimizing the use of limited resources and enhancing the likelihood of project success. PMI Risk Management Study Guide References: The PMI-RMP Exam Content Outline emphasizes the importance of performing quantitative risk analysis, including techniques such as decision tree analysis and EMV calculations, to inform risk response planning and resource allocation.