Business rhythm can fluctuate greatly between different industries and vary between companies within the same industry. What should be used 10 determine how often a project's risk register should be updated or reviewed in a given year when the project is in an industry with a very high business rhythm?
Correct Answer: A
The risk management plan provides guidance on how often the risk register should be updated or reviewed. It takes into account the specific industry, project, and organizational context, including the business rhythm.