When does the Identify Risks process take place in a project?
Correct Answer: D
Explanation/Reference: Explanation: Identify Risks is the process of determining which risks may affect the project. It also documents risks' characteristics. The Identify Risks process is part of the Project Risk Management knowledge area. As new risks may evolve or become known as the project progresses through its life cycle, Identify Risks is an iterative process. The process should involve the project team so that they can develop and maintain a sense of ownership and responsibility for the risks and associated risk response actions. Risk Register is the only output of this process. Incorrect Answers: A, B, C: Identify Risks process takes place at all the stages of a project, because risk changes over time.