What activity should be done for effective post-implementation reviews during the project?
Correct Answer: A
Explanation/Reference: Explanation: For effective post-implementation review the business measurements up front is established during the project. Incorrect Answers: B: Executing sufficient number of business cycles in the new system is done after the completion of the project. C, D: Identifying the information to be reviewed and information collected during each stage of project is done in pre-project phase and not during project for effective post-implementation review.