You are a project manager for your organization and you're working with four of your key stakeholders. One of the stakeholders is confused as to why you're not discussing the current problem in the project during the risk identification meeting. Which one of the following statements best addresses when a project risk actually happens?
Correct Answer: C
Explanation/Reference: Explanation: According to the PMBOK, a project risk is always in the future. If the risk event has already happened, then it is an issue, not a risk. Incorrect Answers: A: You can identify risks before they occur and not after their occurrence. B: Risks can only happen in the future. D: Triggers are warning signs and conditions of risk events, but this answer isn't the best choice for this question.