You are the project manager of the GHT project. You are accessing data for further analysis. You have chosen such a data extraction method in which management monitors its own controls. Which of the following data extraction methods you are using here?
Correct Answer: A
Explanation/Reference: Explanation: Direct extraction from the source system involves management monitoring its own controls, instead of auditors/third parties monitoring management's controls. It is preferable over extraction from the system custodian. Incorrect Answers: B: Extracting data from the system custodian (IT) after system owner approval, involves auditors or third parties monitoring management's controls. Here, in this management does not monitors its own control. C, D: These are not data extraction methods.