Valid CRISC Dumps shared by ExamDiscuss.com for Helping Passing CRISC Exam! ExamDiscuss.com now offer the newest CRISC exam dumps, the ExamDiscuss.com CRISC exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CRISC dumps with Test Engine here:
You are working as the project manager of the ABS project. The project is for establishing a computer network in a school premises. During the project execution, the school management asks to make the campus Wi-Fi enabled. You know that this may impact the project adversely. You have discussed the change request with other stakeholders. What will be your NEXT step?
Correct Answer: C
Explanation/Reference: Explanation: The first step after receiving any change request in a project must be first analyzed for its impact. Changes may be requested by any stakeholder involved with the project. Although, they may be initiated verbally, they should always be recorded in written form and entered into the change management and/or configuration management. Incorrect Answers: A, B, D: All these are the required steps depending on the change request. Any change request must be followed by the impact analysis of the change.