Valid CRISC Dumps shared by ExamDiscuss.com for Helping Passing CRISC Exam! ExamDiscuss.com now offer the newest CRISC exam dumps, the ExamDiscuss.com CRISC exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CRISC dumps with Test Engine here:

Access CRISC Dumps Premium Version
(1745 Q&As Dumps, 35%OFF Special Discount Code: freecram)

<< Prev Question Next Question >>

Question 324/376

You work as a Project Manager for Company Inc. You have to conduct the risk management activities for a project. Which of the following inputs will you use in the plan risk management process?
Each correct answer represents a complete solution. Choose all that apply.

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (376q)
Question 1: Which of the following are true for threats? Each correct an...
Question 2: Which of the following are true for quantitative analysis? E...
Question 3: Which of the following is BEST described by the definition b...
Question 4: You are the project manager of GHT project. You have identif...
Question 5: Which of the following BEST measures the operational effecti...
Question 6: Which of the following are the principles of risk management...
Question 7: You are the project manager in your enterprise. You have ide...
Question 8: Which of the following controls do NOT come under technical ...
Question 9: Wendy has identified a risk event in her project that has an...
Question 10: Ned is the project manager of the HNN project for your compa...
Question 11: You work as a project manager for BlueWell Inc. You are invo...
Question 12: Your project team has completed the quantitative risk analys...
Question 13: Who is at the BEST authority to develop the priorities and i...
Question 14: You are the project manager of GHT project. You have analyze...
Question 15: What are the responsibilities of the CRO? Each correct answe...
Question 16: You are the project manager for GHT project. You need to per...
Question 17: Which of the following characteristics of risk controls answ...
Question 18: Which of the following are risk components of the COSO ERM f...
Question 19: You are the project manager of HWD project. It requires inst...
Question 20: You are the program manager for your organization and you ar...
Question 21: While developing obscure risk scenarios, what are the requir...
Question 22: Which of the following is NOT true for risk governance?...
Question 23: Henry is the project manager of the QBG Project for his comp...
Question 24: Which among the following acts as a trigger for risk respons...
Question 25: Adrian is a project manager for a new project using a techno...
Question 26: You are working as a project manager in Bluewell Inc.. You a...
Question 27: You work as a project manager for BlueWell Inc. You are prep...
Question 28: You are the risk official in Bluewell Inc. You are supposed ...
Question 29: Which of the following business requirements MOST relates to...
Question 30: Which of the following is NOT the method of Qualitative risk...
Question 31: Which of the following should be PRIMARILY considered while ...
Question 32: You are elected as the project manager of GHT project. You a...
Question 33: You are the project manager of the KJH Project and are worki...
Question 34: Which of the following vulnerability assessment software can...
Question 35: Which of the following aspect of monitoring tool ensures tha...
Question 36: You and your project team are identifying the risks that may...
Question 37: In which of the following risk management capability maturit...
Question 38: Which of the following is prepared by the business and serve...
Question 39: You are working in an enterprise. You project deals with imp...
Question 40: Which of the following individuals is responsible for identi...
Question 41: Which of the following risk responses include feedback and g...
Question 42: Harry is the project manager of HDW project. He has identifi...
Question 43: Which of the following events refer to loss of integrity? Ea...
Question 44: You are the project manager for BlueWell Inc. You have notic...
Question 45: Jane, the Director of Sales, contacts you and demands that y...
Question 46: John is the project manager of the HGH Project for her compa...
Question 47: Which of the following is the MOST important objective of th...
Question 48: You are the project manager of HGT project. You have identif...
Question 49: To which level the risk should be reduced to accomplish the ...
Question 50: You are the project manager for Bluewell Inc. You are studyi...
Question 51: Which of the following will significantly affect the standar...
Question 52: A part of a project deals with the hardware work. As a proje...
Question 53: Marie has identified a risk event in her project that needs ...
Question 54: You are the project manager of a project in Bluewell Inc. Yo...
Question 55: You are the project manager of your enterprise. You have int...
Question 56: What are the functions of the auditor while analyzing risk? ...
Question 57: Ben is the project manager of the CMH Project for his organi...
Question 58: Which of the following are the responsibilities of Enterpris...
Question 59: You are the project manager of GHT project. You have impleme...
Question 60: You work as a project manager for BlueWell Inc. You are prep...
Question 61: You are the project manager of your enterprise. While perfor...
Question 62: Which of the following do NOT indirect information?...
Question 63: Fred is the project manager of a large project in his organi...
Question 64: Which section of the Sarbanes-Oxley Act specifies "Periodic ...
Question 65: What are the requirements of monitoring risk? Each correct a...
Question 66: You are working in an enterprise. You enterprise is willing ...
Question 67: Wendy is about to perform qualitative risk analysis on the i...
Question 68: Which among the following acts as a trigger for risk respons...
Question 69: When does the Identify Risks process take place in a project...
Question 70: Which of the following role carriers are responsible for set...
Question 71: You are working in an enterprise. Your enterprise owned vari...
Question 72: You are the risk professional of your enterprise. You need t...
Question 73: You are working with a vendor on your project. A stakeholder...
Question 74: Henry is the project sponsor of the JQ Project and Nancy is ...
Question 75: Which of the following is a key component of strong internal...
Question 76: Stephen is the project manager of the GBB project. He has wo...
Question 77: During qualitative risk analysis you want to define the risk...
Question 78: You are the project manager of GHT project. You are performi...
Question 79: John works as a project manager for BlueWell Inc. He is dete...
Question 80: Which of the following is the MOST effective inhibitor of re...
Question 81: Which of the following role carriers is accounted for analyz...
Question 82: Which of the following is the BEST way to ensure that outsou...
Question 83: You are completing the qualitative risk analysis process wit...
Question 84: You are the project manager for BlueWell Inc. Your current p...
Question 85: The only output of qualitative risk analysis is risk registe...
Question 86: Which one of the following is the only output for the qualit...
Question 87: Which of the following is MOST appropriate method to evaluat...
Question 88: A teaming agreement is an example of what type of risk respo...
Question 89: FISMA requires federal agencies to protect IT systems and da...
Question 90: You are elected as the project manager of GHT project. You h...
Question 91: Suppose you are working in Techmart Inc. which sells various...
Question 92: You are the project manager of a large networking project. D...
Question 93: What is the most important benefit of classifying informatio...
Question 94: Which of the following statements BEST describes policy?...
Question 95: Which of the following processes is described in the stateme...
Question 96: Which of the following IS processes provide indirect informa...
Question 97: You work as a project manager for BlueWell Inc. Your project...
Question 98: When a risk cannot be sufficiently mitigated through manual ...
Question 99: While considering entity-based risks, which dimension of the...
Question 100: You are the project manager of GHT project. You have planned...
Question 101: Jane is the project manager of the NHJ Project for his compa...
Question 102: You are the risk official of your enterprise. You have just ...
Question 103: Which of the following statements is true for risk analysis?...
Question 104: You are the project manager for your organization. You are p...
Question 105: You are the project manager of a project in Bluewell Inc. Yo...
Question 106: Which of the following steps ensure effective communication ...
Question 107: Which of the following methods involves the use of predictiv...
Question 108: What are the requirements of effectively communicating risk ...
Question 109: Suppose you are working in Company Inc. and you are using ri...
Question 110: What is the PRIMARY objective difference between an internal...
Question 111: You are the project manager of GHT project. Your hardware ve...
Question 112: What are the steps that are involved in articulating risks? ...
Question 113: If one says that the particular control or monitoring tool i...
Question 114: Which of the following aspects are included in the Internal ...
Question 115: You are the project manager of the PFO project. You are work...
Question 116: You are the project manager of the HJK Project for your orga...
Question 117: Your project has several risks that may cause serious financ...
Question 118: You are the project manager of GHT project. You have selecte...
Question 119: Della works as a project manager for Tech Perfect Inc. She i...
Question 120: Which of the following role carriers will decide the Key Ris...
Question 121: Billy is the project manager of the HAR Project and is in mo...
Question 122: Which of the following phases is involved in the Data Extrac...
Question 123: You are the project manager for your company and a new chang...
Question 124: Which of the following statements are true for risk communic...
Question 125: Using which of the following one can produce comprehensive r...
Question 126: For which of the following risk management capability maturi...
Question 127: Which of the following come under the management class of co...
Question 128: You are the project manager of a SGT project. You have been ...
Question 129: You are the project manager of HJT project. You want to meas...
Question 130: What are the various outputs of risk response?...
Question 131: Which of the following statements are true for enterprise's ...
Question 132: Which of the following terms is described in the statement b...
Question 133: What are the requirements for creating risk scenarios? Each ...
Question 134: Which of the following is the priority of data owners when e...
Question 135: You are the risk official in Techmart Inc. You are asked to ...
Question 136: Wendy has identified a risk event in her project that has an...
Question 137: Which of following is NOT used for measurement of Critical S...
Question 138: You are the project manager for the NHH project. You are wor...
Question 139: Which of the following control audit is performed to assess ...
Question 140: You are the product manager in your enterprise. You have ide...
Question 141: You are the project manager of GHT project. During the data ...
Question 142: Which of the following processes addresses the risks by thei...
Question 143: Mortality tables are based on what mathematical activity? Ea...
Question 144: Which of the following is the PRIMARY requirement before cho...
Question 145: You are the project manager of the NHQ project in Bluewell I...
Question 146: Which of the following is an output of risk assessment proce...
Question 147: Risks with low ratings of probability and impact are include...
Question 148: Which of the following are the common mistakes while impleme...
Question 149: You work as a Project Manager for www.company.com Inc. You h...
Question 150: Which of the following is NOT true for effective risk commun...
Question 151: Which is the MOST important parameter while selecting approp...
Question 152: Ben works as a project manager for the MJH Project. In this ...
Question 153: Which of the following role carriers is accounted for analyz...
Question 154: Your company is covered under a liability insurance policy, ...
Question 155: There are five inputs to the quantitative risk analysis proc...
Question 156: You are working in Bluewell Inc. which make advertisement We...
Question 157: Which of the following risks is the risk that happen with an...
Question 158: You are the project manager of GHT project. Your project uti...
Question 159: What is the MAIN purpose of designing risk management progra...
Question 160: Which of the following control is used to ensure that users ...
Question 161: Which of the following is the MOST important reason to maint...
Question 162: Which of the following actions assures management that the o...
Question 163: Out of several risk responses, which of the following risk r...
Question 164: You are the project manager of the AFD project for your comp...
Question 165: You are the project manager of HJT project. Important confid...
Question 166: You and your project team have identified a few risk events ...
Question 167: What is the IMMEDIATE step after defining set of risk scenar...
Question 168: Tom works as a project manager for BlueWell Inc. He is deter...
Question 169: You are the Risk Official in Bluewell Inc. You have detected...
Question 170: Which of the following is the MOST critical security conside...
Question 171: Which of the following is the MOST important aspect to ensur...
Question 172: Which of the following techniques examines the degree to whi...
Question 173: A project team member has just identified a new project risk...
Question 174: Which of the following is the MOST important use of KRIs?...
Question 175: Shawn is the project manager of the HWT project. In this pro...
Question 176: Shelly is the project manager of the BUF project for her com...
Question 177: One of the risk events you've identified is classified as fo...
Question 178: Which of the following establishes mandatory rules, specific...
Question 179: Which of the following process ensures that the risk respons...
Question 180: Kelly is the project manager of the NNQ Project for her comp...
Question 181: You are the project manager in your enterprise. You have ide...
Question 182: Which of the following is the FOREMOST root cause of project...
Question 183: Which of the following baselines identifies the specificatio...
Question 184: You work as a Project Manager for Company Inc. You are incor...
Question 185: Thomas is a key stakeholder in your project. Thomas has requ...
Question 186: You are the project manager of GHT project. You have identif...
Question 187: You are an experienced Project Manager that has been entrust...
Question 188: You work as the project manager for Bluewell Inc. Your proje...
Question 189: In which of the following risk management capability maturit...
Question 190: Walter is the project manager of a large construction projec...
Question 191: In the project initiation phase of System Development Life C...
Question 192: You are working in an enterprise. Assuming that your enterpr...
Question 193: What are the three PRIMARY steps to be taken to initialize t...
Question 194: Your project is an agricultural-based project that deals wit...
Question 195: Which of the following are external risk factors? Each corre...
Question 196: Mike is the project manager of the NNP Project for his organ...
Question 197: According to the Section-302 of the Sarbanes-Oxley Act of 20...
Question 198: Your project is an agricultural-based project that deals wit...
Question 199: Beth is a project team member on the JHG Project. Beth has a...
Question 200: Which of the following is the MOST effective inhibitor of re...
Question 201: You work as a project manager for BlueWell Inc. You have dec...
Question 202: Which of the following components of risk scenarios has the ...
Question 203: Which of the following are the security plans adopted by the...
Question 204: Which of the following BEST ensures that a firewall is confi...
Question 205: You are a project manager for your organization and you're w...
Question 206: Which of the following is NOT true for Key Risk Indicators?...
Question 207: Mary is the project manager for the BLB project. She has ins...
Question 208: You are the project manager of a large construction project....
Question 209: You are the risk professional of your enterprise. You have p...
Question 210: You work as the project manager for Bluewell Inc. Your proje...
Question 211: What are the responsibilities of the CRO? Each correct answe...
Question 212: There are four inputs to the Monitoring and Controlling Proj...
Question 213: Which of the following is the BEST way of managing risk inhe...
Question 214: What are the functions of audit and accountability control? ...
Question 215: What activity should be done for effective post-implementati...
Question 216: You have identified several risks in your project. You have ...
Question 217: You are the project manager for TTP project. You are in the ...
Question 218: Malicious code protection is which type control?...
Question 219: Which of the following laws applies to organizations handlin...
Question 220: Which of the following is the most accurate definition of a ...
Question 221: Which of the following represents lack of adequate controls?...
Question 222: A part of a project deals with the hardware work. As a proje...
Question 223: Which of the following is the HIGHEST risk of a policy that ...
Question 224: You work as a project manager for Bluewell Inc. You have ide...
Question 225: The Identify Risk process determines the risks that affect t...
Question 226: Which of the following interpersonal skills has been identif...
Question 227: Which of the following should be considered to ensure that r...
Question 228: Which of the following is true for Cost Performance Index (C...
Question 229: Qualitative risk assessment uses which of the following term...
Question 230: Courtney is the project manager for her organization. She is...
Question 231: What type of policy would an organization use to forbid its ...
Question 232: You are the risk official of your enterprise. Your enterpris...
Question 233: You are the project manager of RFT project. You have identif...
Question 234: David is the project manager of HRC project. He concluded wh...
Question 235: Which of the following processes is described in the stateme...
Question 236: You are the project manager of the GHT project. This project...
Question 237: Sammy is the project manager for her organization. She would...
Question 238: What is the process for selecting and implementing measures ...
Question 239: You are the project manager of GHT project. A risk event has...
Question 240: Which of the following statements is NOT true regarding the ...
Question 241: Which of the following comes under phases of risk management...
Question 242: You are the project manager of GHT project. A stakeholder of...
Question 243: You are the project manager of GHT project. You have applied...
Question 244: What are the PRIMARY requirements for developing risk scenar...
Question 245: Which of the following risks refer to probability that an ac...
Question 246: You are the project manager of project for a client. The cli...
Question 247: You work as a project manager for SoftTech Inc. You are work...
Question 248: Which of the following components ensures that risks are exa...
Question 249: You work as a project manager for BlueWell Inc. You are abou...
Question 250: You work as a project manager for BlueWell Inc. You have dec...
Question 251: Capability maturity models are the models that are used by t...
Question 252: You are the project manager of the GHY project for your orga...
Question 253: Which of the following matrices is used to specify risk thre...
Question 254: You are using Information system. You have chosen a poor pas...
Question 255: Which of the following is the final step in the policy devel...
Question 256: You are the project manager of your enterprise. You have int...
Question 257: Which of the following is the MOST effective method for indi...
Question 258: Which of the following is the BEST way to ensure that outsou...
Question 259: You are preparing to complete the quantitative risk analysis...
Question 260: Which of the following is true for risk management framework...
Question 261: Which of the following processes addresses the risks by thei...
Question 262: Your project spans the entire organization. You would like t...
Question 263: You and your project team are identifying the risks that may...
Question 264: Which of the following are sub-categories of threat? Each co...
Question 265: You are the project manager of HFD project. You have identif...
Question 266: You are the project manager of your project. You have to ana...
Question 267: When it appears that a project risk is going to happen, what...
Question 268: Judy has identified a risk event in her project that will ha...
Question 269: You are the project manager of RFT project. You have identif...
Question 270: Which of the following is the best reason for performing ris...
Question 271: You are the project manager of the NNN Project. Stakeholders...
Question 272: Which of the following BEST describes the utility of a risk?...
Question 273: Which of the following nodes of the decision tree analysis r...
Question 274: You are the project manager of a HGT project that has recent...
Question 275: You are the project manager of the QPS project. You and your...
Question 276: Which of the following is a performance measure that is used...
Question 277: Where are all risks and risk responses documented as the pro...
Question 278: Which negative risk response usually has a contractual agree...
Question 279: Which of the following is the first MOST step in the risk as...
Question 280: Which of the following is the process of numerically analyzi...
Question 281: How are the potential choices of risk based decisions are re...
Question 282: Which of the following is true for Single loss expectancy (S...
Question 283: You are the project manager of the NHH Project. You are work...
Question 284: What is the value of exposure factor if the asset is lost co...
Question 285: Which of the following is true for Single loss expectancy (S...
Question 286: Risks to an organization's image are referred to as what kin...
Question 287: David is the project manager of the HRC Project. He has iden...
Question 288: Which of the following statements are true for enterprise's ...
Question 289: What is the value of exposure factor if the asset is lost co...
Question 290: You are the project manager of your enterprise. You have ide...
Question 291: Jeff works as a Project Manager for www.company.com Inc. He ...
Question 292: An interruption in business productivity is considered as wh...
Question 293: You are the project manager for your organization to install...
Question 294: Which of the following statements is NOT true regarding the ...
Question 295: Which of the following is the BEST defense against successfu...
Question 296: Which of the following process ensures that extracted data a...
Question 297: You work as the project manager for Company Inc. The project...
Question 298: You work as a project manager for TechSoft Inc. You are work...
Question 299: Which of the following should be PRIMARILY considered while ...
Question 300: Which of the following characteristics of risk controls can ...
Question 301: Natural disaster is BEST associated to which of the followin...
Question 302: Which of the following controls focuses on operational effic...
Question 303: You are the risk official at Bluewell Inc. There are some ri...
Question 304: Which of the following risks is associated with not receivin...
Question 305: Which of the following items is considered as an objective o...
Question 306: What is the FIRST phase of IS monitoring and maintenance pro...
Question 307: You are the project manager of the NHH Project. You are work...
Question 308: You are working on a project in an enterprise. Some part of ...
Question 309: John is the project manager of the NHQ Project for his compa...
Question 310: Which of the following is an acceptable method for handling ...
Question 311: Which of the following serve as the authorization for a proj...
Question 312: Which of the following considerations should be taken into a...
Question 313: You are the project manager of GHT project. You identified a...
Question 314: You are the administrator of your enterprise. Which of the f...
Question 315: Which of the following is true for risk evaluation?...
Question 316: You have been assigned as the Project Manager for a new proj...
Question 317: Which of the following control detects problem before it can...
Question 318: You are the project manager of your enterprise. You have ide...
Question 319: You are the project manager of the GHT project. You are acce...
Question 320: Which of the following is the priority of data owners when e...
Question 321: Out of several risk responses, which of the following risk r...
Question 322: Which of the following is an administrative control?...
Question 323: You are the risk professional of your enterprise. Your enter...
Question 324: You work as a Project Manager for Company Inc. You have to c...
Question 325: You are the project manager of GHT project. You have initiat...
Question 326: Where are all risks and risk responses documented as the pro...
Question 327: How residual risk can be determined?...
Question 328: Which of the following is the greatest risk to reporting?...
Question 329: You are the project manager of GHT project. You want to perf...
Question 330: What type of policy would an organization use to forbid its ...
Question 331: Which of the following documents is described in the stateme...
Question 332: You are the risk official in Techmart Inc. You are asked to ...
Question 333: An enterprise has identified risk events in a project. While...
Question 334: During which of the following processes, probability and imp...
Question 335: Jenny is the project manager for the NBT projects. She is wo...
Question 336: In which of the following conditions business units tend to ...
Question 337: You are the IT manager in Bluewell Inc. You identify a new r...
Question 338: What is the PRIMARY need for effectively assessing controls?...
Question 339: You are the project manager of GFT project. Your project inv...
Question 340: John works as a project manager for BlueWell Inc. He is dete...
Question 341: Your project change control board has approved several scope...
Question 342: You have been assigned as the Project Manager for a new proj...
Question 343: Which of the following come under the phases of risk identif...
Question 344: You work as the project manager for Bluewell Inc. There has ...
Question 345: Mary is a project manager in her organization. On her curren...
Question 346: Which of the following is a technique that provides a system...
Question 347: You are the project manager of GHT project. Your hardware ve...
Question 348: Which of the following processes is described in the stateme...
Question 349: What are the key control activities to be done to ensure bus...
Question 350: NIST SP 800-53 identifies controls in three primary classes....
Question 351: You are the project manager of the HGT project in Bluewell I...
Question 352: Which among the following is the MOST crucial part of risk m...
Question 353: What are the two MAJOR factors to be considered while decidi...
Question 354: Which of the following are the principles of access controls...
Question 355: Which of the following is NOT true for risk management capab...
Question 356: Which of the following decision tree nodes have probability ...
Question 357: Which of the following is the BEST method for discovering hi...
Question 358: Which of the following parameters are considered for the sel...
Question 359: You are the risk control professional of your enterprise. Yo...
Question 360: What are the PRIMARY objectives of a control?...
Question 361: Which of the following assets are the examples of intangible...
Question 362: Which of the following controls is an example of non-technic...
Question 363: Which of the following operational risks ensures that the pr...
Question 364: Assessing the probability and consequences of identified ris...
Question 365: Which among the following is the BEST reason for defining a ...
Question 366: You are using Information system. You have chosen a poor pas...
Question 367: Which of the following type of risk could result in bankrupt...
Question 368: Which of the following role carriers has to account for coll...
Question 369: Which of the following parameters would affect the prioritiz...
Question 370: What are the functions of audit and accountability control? ...
Question 371: Which of the following is the way to verify control effectiv...
Question 372: You are the project manager of GRT project. You discovered t...
Question 373: You are working as the project manager of the ABS project. T...
Question 374: Which of the following test is BEST to map for confirming th...
Question 375: You are the risk professional in Bluewell Inc. A risk is ide...
Question 376: Which of the following BEST ensures that a firewall is confi...