Explanation/Reference:
Explanation:
The inputs to the plan risk management process are as follows:
Project scope statement: It provides a clear sense of the range of possibilities associated with the

project and establishes the framework for how significant the risk management effort may become.
Cost management plan: It describes how risk budgets, contingencies, and management reserves will

be reported and accessed.
Schedule management plan: It describes how the schedule contingencies will be reported and

assessed.
Communication management plan: It describes the interactions, which occurs on the project and

determines who will be available to share information on various risks and responses at different times.
Enterprise environmental factors: It include, but are not limited to, risk attitudes and tolerances that

describe the degree of risk that an organization withstand.
Organizational process assets: It includes, but are not limited to, risk categories, risk statement formats,

standard templates, roles and responsibilities, authority levels for decision-making, lessons learned, and stakeholder registers.
Incorrect Answers:
A: It is not an input for Plan risk management process.