You are the project manager of a SGT project. You have been actively communicating and working with the project stakeholders. One of the outputs of the "manage stakeholder expectations" process can actually create new risk events for your project. Which output of the manage stakeholder expectations process can create risks?
Correct Answer: C
Explanation/Reference: Explanation: The manage stakeholder expectations process can create change requests for the project, which can cause new risk events to enter into the project. Change requests are requests to expand or reduce the project scope, modify policies, processes, plans, or procedures, modify costs or budgets or revise schedules. These requests for a change can be direct or indirect, externally or internally initiated, and legally or contractually imposed or optional. A Project Manager needs to ensure that only formally documented requested changes are processed and only approved change requests are implemented. Incorrect Answers: A: The project management plan updates do not create new risks. B: The organizational process assets updates do not create new risks. D: The project document updates do not create new risks.