Valid CRISC Dumps shared by ExamDiscuss.com for Helping Passing CRISC Exam! ExamDiscuss.com now offer the newest CRISC exam dumps, the ExamDiscuss.com CRISC exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CRISC dumps with Test Engine here:
You work as the project manager for Bluewell Inc. Your project has several risks that will affect several stakeholder requirements. Which project management plan will define who will be available to share information on the project risks?
Correct Answer: C
is incorrect. The stakeholder management strategy does not address risk communications. Answer: A is incorrect. The Risk Management Plan defines risk identification, analysis, response, and monitoring. Answer: D is incorrect. The Resource Management Plan does not define risk communications.