Judy has identified a risk event in her project that will have a high probability and a high impact. Based on the requirements of the project, Judy has asked to change the project scope to remove the associated requirement and the associated risk. What type of risk response is this?
Correct Answer: C
is incorrect. Exploit risk response is used for positive risk or opportunity, not for negative risk. Answer:D is incorrect. Transference allows the risk to be transferred, not removed from the project, to a third party. Transference usually requires a contractual relationship with the third party. Answer:B is incorrect. This risk response does require a change request, in some instances, but it's the avoidance risk response and not just a change request.