You are the project manager for your company and a new change request has been approved for your project. This change request, however, has introduced several new risks to the project. You have communicated these risk events and the project stakeholders understand the possible effects these risks could have on your project. You elect to create a mitigation response for the identified risk events. Where will you record the mitigation response?
Correct Answer: A
is incorrect. The risk management plan is an input to the risk response planning, but it is not the best choice for thisquestionoption B is incorrect. This is not a valid choice for thequestionoption C is incorrect. The project management plan is the parent of the risk management plan, but the best choice is the risk register.