Valid CRISC Dumps shared by ExamDiscuss.com for Helping Passing CRISC Exam! ExamDiscuss.com now offer the newest CRISC exam dumps, the ExamDiscuss.com CRISC exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CRISC dumps with Test Engine here:
Shelly is the project manager of the BUF project for her company. In this project Shelly needs to establish some rules to reduce the influence of risk bias during the qualitative risk analysis process. What method can Shelly take to best reduce the influence of risk bias?
Correct Answer: D
Section: Volume B Explanation: By establishing definitions for the level of probability and impact a project manager can reduce the influence of bias. Incorrect Answers: A: This is not a valid statement for reducing bias in the qualitative risk analysis. B: Positive and negative stakeholders are identified based on their position towards the project goals and objectives, not necessarily risks. C: Root cause analysis is a good exercise, but it would not determine risk bias.