You are an experienced Project Manager that has been entrusted with a project to develop a machine which produces auto components. You have scheduled meetings with the project team and the key stakeholders to identify the risks for your project. Which of the following is a key output of this process?
Correct Answer: A
D, and C are incorrect. All these are outputs from the "Plan Risk Management" process, which happens prior to the starting of risk identification.