Harry is the project manager of HDW project. He has identified a risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project so he hires a professional vendor to complete this portion of the project work. What type of risk response is Harry implementing?
Correct Answer: A
is incorrect. Avoidance removes the risk event entirely either by adding additional steps to avoid the event or reducing the project scope. Answer:C is incorrect. Mitigation are actions that Harry's project team could take to reduce the probability and/or impact of a risk event. Answer:B is incorrect. Risk acceptance means that no action is taken relative to a particular risk; loss is accepted if it occurs. Here Harry is not accepting this risk event; he does not want anyone of his team to become injured so he's transferring the event to professional vendor.