Which date type should an assignee update to change the completion date of a task?
Correct Answer: C
In Workfront, to update the planned completion of a task, the assignee should modify the "Planned Completion Date." This date is used for scheduling and planning purposes to track when the task is expected to be finished. Changing the "Planned Completion Date" adjusts the task's projected timeline and allows for a recalculation of project dependencies.