Valid AD0-E903 Dumps shared by ExamDiscuss.com for Helping Passing AD0-E903 Exam! ExamDiscuss.com now offer the newest AD0-E903 exam dumps, the ExamDiscuss.com AD0-E903 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com AD0-E903 dumps with Test Engine here:
Given this information regarding a Task: * Planned Start Date: May 14 * Actual Start Date: May 14 * Planned Completion Date: May 20 * Projected Completion Date: May 22 * Percent Complete: 50% * Duration: 5 Days * Planned Hours: 8 Hours * Status: In Progress If today's date were May 19, what would be the Task's progress status?
Correct Answer: C
In Workfront, when the projected completion date exceeds the planned completion date and the task is only 50% complete by May 19, it is automatically flagged as "At Risk." This alerts the project manager that the task is not progressing according to the original plan, potentially causing delays in the project timeline.