A project sponsor has asked to see a summary of all projects that they are the sponsor of which were completed in the past year. The project sponsor wants to see the information grouped by the month the project was completed. What steps should the project manager take to create this view?
Correct Answer: A
The best approach is to generate a Project Report in Workfront, where the report filters the Actual Completion Date for the past year and groups projects by the Sponsor and the month of completion. This allows the sponsor to see exactly which projects they sponsored and when they were completed within the selected timeframe. Grouping by month provides a clear visual of the completion timeline.