Valid AD0-E903 Dumps shared by ExamDiscuss.com for Helping Passing AD0-E903 Exam! ExamDiscuss.com now offer the newest AD0-E903 exam dumps, the ExamDiscuss.com AD0-E903 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com AD0-E903 dumps with Test Engine here:
A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied. Which date type would the project manager utilize?
Correct Answer: B
The "Projected Date" in Workfront reflects the most likely completion date of a task based on the task's progress and any predecessors. Unlike the "Planned Date," which is set manually, the Projected Date automatically updates as task progress changes, giving a real-time estimate of task completion.