Valid AD0-E903 Dumps shared by ExamDiscuss.com for Helping Passing AD0-E903 Exam! ExamDiscuss.com now offer the newest AD0-E903 exam dumps, the ExamDiscuss.com AD0-E903 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com AD0-E903 dumps with Test Engine here:
A team lead needs to regularly report on the adherence of budget and timeline of a group of projects. What should the team lead use to organize these projects to allow them to be tracked together?
Correct Answer: B
In Workfront, a "Program" is used to group related projects that share a common objective or need to be tracked together, such as adherence to budget and timeline. Programs allow for collective reporting on these projects, making it easier for team leads to monitor progress, manage resources, and report on key performance indicators (KPIs) across multiple projects.