Valid AD0-E903 Dumps shared by ExamDiscuss.com for Helping Passing AD0-E903 Exam! ExamDiscuss.com now offer the newest AD0-E903 exam dumps, the ExamDiscuss.com AD0-E903 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com AD0-E903 dumps with Test Engine here:
A company has decided that all projects for the year need to be created from templates and staffed in the following quarter. The projects will need to remain in a backlog until the team has capacity to work on them. There has been confusion previously because the team used Planning status for all work not started. What should the project manager do to help the team see the difference between work in the backlog versus work that is now being planned?
Correct Answer: C
In Workfront, creating a custom status specifically for "Backlog" allows the team to differentiate between work that is pending capacity and work that is actively being planned. This prevents confusion and allows for better project tracking, ensuring that tasks move smoothly from backlog to the planning phase when appropriate.