Valid AD0-E903 Dumps shared by ExamDiscuss.com for Helping Passing AD0-E903 Exam! ExamDiscuss.com now offer the newest AD0-E903 exam dumps, the ExamDiscuss.com AD0-E903 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com AD0-E903 dumps with Test Engine here:
Task 2 has a 5-day duration, is tied to Task 1 with a predecessor, and is expected to begin once Task 1 is completed. Due to a resource availability conflict, Task 1 was rescheduled to start 1 week later. Once Task 1 was rescheduled, the planned start date on Task 2 did not dynamically shift by 5 days as expected but instead remained the same planned start date that existed before the change to Task 1. What may have caused the planned start date of Task 2 to remain the same?
Correct Answer: B
In this scenario, the fact that Task 2's start date did not shift automatically despite its dependency on Task 1 suggests that a manual override was applied, resulting in a Task Constraint of "Must Start On." This type of constraint locks a task to a specific date, preventing it from dynamically adjusting based on changes to its predecessor. The other options either do not explain why the start date remained static or involve user-specific scheduling conflicts, which would not affect the system-driven date adjustment.