When a defect is discovered during the test phase., what is the earliest phase in the software lifecycle that could need rework to resolve the defect?
Correct Answer: C
When a defect is discovered during the test phase, the earliest phase in the software lifecycle that could need rework to resolve the defect is often the requirements phase because: * Root Cause Analysis: Many defects originate from misunderstandings or errors in the initial * requirements. If the requirements are incorrect or incomplete, it will affect all subsequent phases. * Impact on Design and Implementation: Incorrect requirements lead to flawed design and implementation, necessitating rework in these phases as well. * Cost of Fixing Defects: The cost and effort to fix defects increase exponentially the later they are found in the development lifecycle. Addressing issues at the requirements stage is more cost-effective.