An organization uses the plan-do-check-act (PDCA) cycle to align its processes to an international quality standard, which of the following activities would be performed during the "act" step?
Correct Answer: C
PDCA Cycle Overview:The Plan-Do-Check-Act (PDCA) cycle is a continuous improvement process used to align processes with quality standards. Act Phase:In the 'Act' step, the organization acts on the findings from the 'Check' step to implement changes that improve the process. This typically involves making revisions to the quality system. Quality Improvements:By making revisions based on the findings from audits and performance evaluations, the organization continuously improves its processes and aligns them better with international standards.