What is the correct statement about Work in Process (WIP)?
Correct Answer: C
Lowering WIP limits reduces multitasking, exposes bottlenecks, and encourages team members to collaborate to finish work before starting new work. This is a core Lean and SAFe principle to increase flow and throughput. A is incorrect; excessive WIP delays feedback. B is incorrect; WIP is highly related to utilization and flow. References: SAFe 6.0 Website: Team Kanban SPC 6.0 Guide: "Lowering WIP limits increases collaboration and speeds up flow."