Phase-gate Milestones are not a good predictor of project performance.
Correct Answer: A
SAFe and Lean-Agile principles recognize that traditional phase-gate milestones (sign-offs at project checkpoints) do not accurately predict or ensure performance or outcomes. Empirical milestones-based on actual, working systems-are favored. "Phase-gate milestones are not good predictors of progress or project performance; Lean-Agile development relies on objective evaluation of working systems." (Source: SAFe 6.0 Framework: Lean-Agile Milestones)