Valid SAFe-SPC Dumps shared by ExamDiscuss.com for Helping Passing SAFe-SPC Exam! ExamDiscuss.com now offer the newest SAFe-SPC exam dumps, the ExamDiscuss.com SAFe-SPC exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com SAFe-SPC dumps with Test Engine here:
During PI Planning, which of the following exposes dependencies between teams that may require coordination?
Correct Answer: C
The ART Planning Board is a visual tool used during PI Planning to highlight and track dependencies between teams. Teams use it to indicate where their work is dependent on others, which helps surface and coordinate cross-team dependencies for successful PI execution. References: SAFe 6.0, "PI Planning" article (ART Planning Board) SPC 6.0 Practice Guide, "Launching an Agile Release Train"