An organization is executing two projects - Project A and Project B - simultaneously. A previously identified risk will impact the schedule for Project A. While executing the mitigation plan, a number of residual risks are identified that could provide cost savings for Project B. Which action should the risk manager for Project A take?
Correct Answer: B
Collaborating with other project risk managers ensures cross-project opportunities and risks are leveraged or mitigated appropriately. The PMBOK Guide encourages this approach: " When risks or opportunities cross project boundaries, risk managers should consult with other project teams to identify synergies and dependencies. " - PMBOK Guide, 6th Edition, Section 11.1 References: PMBOK Guide, 6th Edition, Section 11.1