A project team is leading a software development project. During the project kickoff meeting, the risk manager discovers that a vendor has not finalized the timeline for delivering an essential component. This creates uncertainty in the overall project schedule. What should the risk manager do to address the risk?
Correct Answer: A
Best practice in risk management is to immediately assess the impact of identified risks and develop appropriate response plans. The PMBOK Guide confirms: " When a risk is identified, its impact and likelihood should be assessed as soon as possible, and risk response strategies developed and agreed upon. " - PMBOK Guide, 6th Edition, Section 11.5 This is especially important for critical dependencies such as vendor deliverables. References: PMBOK Guide, 6th Edition, Section 11.5 ISO 31000:2018, Section 6.5