A project is in progress when the product team requests a change to the scope. The team indicates that this is a minimal change and should not create any problems. What should the risk manager do next?
Correct Answer: B
Any change to project scope, regardless of perceived size, should trigger a risk analysis to determine potential impact. The PMBOK Guide states: "When a change request is submitted, it should be evaluated for potential impact on project objectives, including risk. Analysis of impact is a best practice before implementing any change." - PMBOK Guide, 6th Edition, Section 4.6.2 (Perform Integrated Change Control) This ensures that the team does not overlook risks associated with even "minimal" changes. References: PMI PMBOK Guide, 6th Edition, Section 4.6 Practice Standard for Project Risk Management, PMI, Section 5.5