Valid PMI-RMP Dumps shared by EduDump.com for Helping Passing PMI-RMP Exam! EduDump.com now offer the newest PMI-RMP exam dumps, the EduDump.com PMI-RMP exam questions have been updated and answers have been corrected get the newest EduDump.com PMI-RMP dumps with Test Engine here:
A risk manager schedules workshops for identifying risks about an initiative involving multiple business units, recruitments for different roles, procurements, technological uplift, training, and changes in the ways of working. Who should participate in the risk management activity?
Correct Answer: B
Including both internal and external stakeholders ensures diverse perspectives and comprehensive risk identification. PMBOK Guide states: "Stakeholder participation, including both internal and external stakeholders, is essential during risk identification to ensure a broad and complete identification of risks." - PMBOK Guide, 6th Edition, Section 11.2 References: PMBOK Guide, 6th Edition, Section 11.2