A risk manager is collaborating with project stakeholders and the project team to identify risks in a construction project. The risk manager intends to use an approach that engages stakeholders based on information, such as scope baseline and project estimates, while also determining risk impacts based on this approach. Which risk identification approach should the risk manager use to achieve this goal?
Correct Answer: D
Assumptions and constraints analysis focuses on reviewing project documents (scope baseline, estimates, etc.) to determine what is assumed or constrained, and then assesses the risks arising from those assumptions and constraints. The PMBOK Guide describes: "Assumptions and constraints analysis explores the validity of project assumptions and constraints, as documented in scope baselines and estimates, and evaluates their potential impact on project objectives." - PMBOK Guide, 6th Edition, Section 11.2.2.2 References: PMBOK Guide, 6th Edition, Section 11.2.2.2