You are a project manager in an organization that uses Project Server 2013. You manage two projects named Proj1 and Proj2.
You create a deliverable dependency between both projects by taking the following actions:
You create a deliverable named Deliverable1 against a milestone named Milestone1 in Proj1. The

Finish date for Milestone1 and the Deliverable Finish date for Deliverable1 are the same.
On Proj2, you associate a dependency that has a milestone named Milestone2 to the Deliverable1.

After several days of work, Proj1 has been rescheduled, which moves the Finish date for Milestone1 ahead by five days.
You need to ensure that these changes are reflected in both projects.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)